Canoe Building Time-Line by John Lindman
 
Prepare Site - Day One 
  
   509-327-7902 voice and fax       
   barkcanoe@earthlink.net e-mail
  
  
	Home    
	Canoes   
	Classes    
	Materials   
	Accessories    
	News and Stuff   
	Links   
	Consignment Canoes
	Awning, fire pit, table, building bed, tank, heater
Prepare Root - Day One & Day Two
	Insert in pot, bring to boil and let sit for 3 hours
	Split
	Remove bark
Prepare Thwarts	- Day Three
	Carve
Prepare Gunwales - Day Three
	Bevel Inside Gunwale
	Laminate Ends
	Bend Ends
Prepare Stem Pieces - Day Three
	Carve
	Laminate
	Bend
Prepare Sheathing - Day Four
	Split blanks down for ribs and sheathing
	Make sheathing blanks and then soak them
	Pick out the various pieces and where they will go
	Soak it
Prepare Ribs - Day Five
	Split rib blanks
	Carve ribs
	
Final prep of root and sheathing - Day Five
	Final split and trim of sheathing pieces.  
	(Carve as necessary to get all pieces consistent in thickness)
	Do final prep of sheathing - get each root consistent in size with all others
Roll-out Bark - Day Six
	Weight it down
	Cut gores
	Bring up sides
	Insert side panels
	Stake into place
	Check
Stitch - Day  Seven & Eight
	Mark line
	Mark holes
	Peg
	Stitch
Insert Gunwales - Day Nine
	Release inside stakes
	Insert gunwales
	Height Sticks
	Clamp
	Check
	
Lash Gunwales - Days Nine & Ten
	Peg
	Lash (to end thwart)
Insert Stems - Day Eleven
	Peg one side
	Trim bark
	Peg other
	Trim half way
	Remove Frame
Insert Permanent Thwarts - Day Twelve
	Make Mortise
	Insert
	Peg
Turn-up and Lash Gunwale Ends - Day Twelve
	Make cardboard template
	Trim bark
	Lash
	Do fancy lashing at end of gunwales or do bark deck
Bend Ribs - Day Thirteen
	Bend
	Install binder
	Place in sun to dry
Pitch Inside - Day Fourteen
	Prepare canvas
	Mark all inside holes with felt pen
	Pitch
	Cover w/canvas
Insert Ribs and Sheathing - Day Fourteen
Insert Ashleaf or man-board - Day Fourteen
	Carve
	Fit
Apply Gunwale Cap - Day Fifteen
	Make Pegs
	Drill & Fit
	Lash ends
Pitch outside - Day Fifteen
	Prepare pitch
	Pitch
Test - Day Fifteen
	Place on saw horses
	Add about an inch of water
	Go underneath canoe and mark with pencil any leaks 
	(slosh water around to check all necessary areas)
	Pitch as needed  Maiden voyage!